Project Challenges and Solutions
Different access conditions
The two elevations required different access methods. One side allowed a MEWP, while the other could not be reached using ladders under the site rules. The team used MEWPs operated by IPAF-trained personnel where suitable and a mobile access tower on the restricted side, matching the access method to each elevation.
Preparation before coating
The aluminium frames needed to be thoroughly cleaned before spraying so the coating could bond properly. A reach-and-wash system with RO water was used to remove dirt and surface contamination without slowing the programme.
Public-facing location
Because the property sits in a busy urban setting, the work had to be managed around nearby foot traffic. Exclusion zones, tidy working areas and low-odour coating methods helped reduce disruption and protect the public.
Safety controls
Spraying at height in a populated area required clear planning. RAMS were approved before the start, PPE requirements were followed on site, and the team held regular briefings to keep each stage controlled.
Process
The project started with access set-up, site protection and confirmation of the agreed safety measures. The window frames were then cleaned using the RO reach-and-wash system. Once dry, glazing and surrounding surfaces were masked, with additional protection at ground level to manage overspray risk.
The aluminium frames were sprayed using Zinfos 490 through an airless system, with coats applied evenly across both elevations. After application, masking was removed, the site was cleared and the finish was inspected before handover.
Results
The building now has a cleaner, more modern appearance, with a consistent sprayed finish across the aluminium frames. The works were delivered without disruption to neighbouring areas, while the mixed access strategy allowed both elevations to be completed safely and efficiently.
Request a Tailored Quotation.

Refurbs delivered an excellent transformation of the building. The finish exceeded our expectations, communication was first class throughout, and the project was completed professionally with minimal disruption to the site.
Connor
2 Evelyn Street Project Team
Specialist Aluminium Frame Spraying For Commercial Buildings
Aluminium frame spraying can renew the appearance of serviceable glazing systems where a colour or finish change is needed. Preparation, a compatible coating specification and planned access are essential; the work and any temporary restrictions should be agreed around the building's use.

projects

Shepperton Studios; Large-Scale Cladding Spray Painting Project

Commercial Warehouse Cladding Refurbishment | Wembley, London